I-75 Interstate Bridge

I-75 Interstate Bridge

Sidney, Ohio, United States
Bridge abutment service life extension through galvanic encasement
Owner: Ohio Department of Transportation

In 2005, the Ohio Department of Transportation District 7 conducted an experiment with the objective of finding a method to get ahead of a seemingly constant substructure repair cycle.  This experiment replaced the normal process of performing substructure patch repairs with an abutment refacing strategy containing galvanic cathodic protection.  Prior to employing this strategy, the District struggled to keep up with the number of bridges needing repairs because the area adjacent to the last repairs would require repair within 5 to 7 years.  

The Problem

With 1408 bridges to maintain, they just couldn’t sustain the increasing rate of maintenance repair projects each year to keep up with the deterioration rate.  When they fell behind, the substructure would deteriorate to a point where the abutment would need to be replaced.  However, the decks that had a concrete or asphalt-wearing course normally had minimal distress and years of remaining service life.

Many of these older bridges carry Interstate 75 (I-75) through the district.  I-75 is a major north-south highway that runs 1,786 miles from the Great Lakes to the Southeast regions of the United States.  It begins at the Canadian border at Sault Ste. Marie, Michigan and ends near Miami, Florida.  Maintenance of the bridges is key to keeping heavy commercial and noncommercial traffic flowing on this important route.

Abutment condition prior to repair, May 2005
Abutment condition prior to repair, May 2005

Corrosion of Reinforcing Steel in Concrete

It has become common for abutments to experience concrete damage and deterioration on these slab bridges.  Corrosion was the cause of failing abutments due to the deck joint being directly over the abutment.  The joint seals would fail, allowing deicing salt, grit and water to enter the joint and contaminate the abutment stem wall.  These typical 1950s vintage slab bridges would have a 19 to 22-inch thick slab cast into a key joint at the top of the abutment.  As the deck would cool in the winter, thermal contraction would put tension on the key as it pulled the abutment stem walls toward each other.  This likely initiated a crack at the base of the key that accelerated salt contamination of the stem wall reinforcing.  Once corrosion started, the top of the stem wall would spall. 

Original 1950's stem wall detail
Original 1950's stem wall detail

Our Solution

The options considered to fix the ailing abutments were:

  • Do Nothing - Not a feasible alternative for deficient bridges on the interstate system
  • Repair bridge - With appropriate repair, most of these bridges have remaining service life
  • Replace bridge - Not cost-effective to remove a good slab, and extremely disruptive to traffic
Dowels and Galvashield DAS installed

In 2005, The District Bridge Engineer strategized that if the entire abutment were repaired in such a manner that the repairs could last 20 years, it would allow the District to get ahead of the repair cycle, allowing the District more time to program bridge replacement.  The intent of this strategy was to provide additional service life to the abutment to match or exceed the remaining service life of the deck.  The solution developed was an abutment refacing strategy using self-consolidating concrete with galvanic cathodic protection to prevent reoccurring corrosion activity, allow thermal joint movement, and reestablish the slab-bearing surface. 

The Results

One of the keys to longevity was the use of galvanic anodes in the repairs.  The Galvashield DAS is an alkali-activated zinc anode encased in a mortar shell.  The anodes were sized to protect the existing reinforcing under the joint for a minimum of 20-years of service life.

Abutment of I-75 Bridge over Kirkwood Road (mm 87) July 2005
Abutment of I-75 Bridge over Kirkwood Road (mm 87) July 2005

Sustainability:

Over the last 18 years, the bridges included in the ODOT refacing experiment have performed remarkably well, eliminating two full 7-year repair cycles so far and appearing to have many more years of service to go. This strategy has proven exceptional progress in the way of sustainability by both reducing the natural resources consumed and reducing the growth of their yearly bridge maintenance costs. 

Abutment of I-75 Bridge over Kirkwood Road (mm 87) in 2022 (Note efflorescence from leaking joint and weep holes)
Abutment of I-75 Bridge over Kirkwood Road (mm 87) in 2022 (Note efflorescence from leaking joint and weep holes)

Technology Used

These innovative products and technologies were used on this project. 

 

1 Technology
We use cookies to ensure you get the best experience on our website. By using this site, you agree to these cookies being set. To learn more, read our privacy policy.
View policyOk